datewhat
. september 15th .
1st full draft of each deliverable should be available for internal review
september 27th
Final version of all technical deliverables should be sent to the Technical Coordinator
Dates below have been set by the Commission (see here)
september 30th
Final version of all technical deliverables should be on the Artist website, for pre-assesment by the reviewers.
october 15th
All technical deliverables NOT available on the ARTIST2 web site are REJECTED (this is a contractual requirement)
Also, all management deliverables MUST be available on the ARTIST2 web site. If any are missing, the review meeting is CANCELLED.