Year4 Review

December 11-12, 2008       Brussels, Belgium

Dues Dates for Technical Deliverables, and Financial Reporting

Technical Deliverables
datewhat
. Sept 15th 2008 .
Technical Coordinator can start to provide early assessments of 1st full drafts of the deliverables. Send the documents here.
. Sept 30th 2008 .
Deliverables should be available for formal assessment by the internal reviewers (Artist2 members not working on the cluster/activity, chosen by the cluster/activity leader)
Oct 15th 2008
Final version of all technical deliverables should be sent to the Technical Coordinator
Dates below have been set by the Commission (see page 11 of the Year3 Review Report)
Oct 30th 2008
Final version of all technical deliverables should be on the Artist website, for pre-assesment by the reviewers.
Nov 15th 2008
All technical deliverables NOT available on the ARTIST2 web site are REJECTED (this is a contractual requirement)
Also, all management deliverables MUST be available on the ARTIST2 web site by November 15th, 2008. If any are missing, the review meeting is CANCELLED.

 

 

Financial Reporting
datewhat
Oct 15th 2008
Initial versions of all financial reporting documents should be sent to Frédéric Vollé
Dates below have been set by the Commission (see page 11 of the Year3 Review Report)
Oct 30th 2008
Final version of all financial deliverables should be on the Artist website, for pre-assesment.
. Nov 15th 2008 .
All financial deliverables NOT available on the ARTIST2 web site are REJECTED (this is a contractual requirement)
Also, all management deliverables MUST be available on the ARTIST2 web site by November 15th, 2008. If any are missing, the review meeting is CANCELLED.